Operating rules of the automatic cutting line and tin dipping machine:
1. Turn on the power, and pull the cutting wire to the right of the blade through the wire feeder.
2. Set the required specifications (change according to the part number)
3. First cut out one or two pieces for measurement. Check whether there is any broken wire.
4. After the setting is completed, press the "Start" button to start the job.
5. After the first wire is judged to meet the production quality after QC inspection, press "Start" to start the production operation. During the production process, if there is an abnormal situation, press the emergency stop button immediately, and immediately report to the shift (group) leader or machine repair. .
6. After cutting the line, turn off the machine, use an air gun to clean the machine, and do a good job of maintenance, and at the same time do the "5S" work in the workplace.
Precautions for the automatic cutting line and tin dipping machine
1. The cutting machine must be operated by trained personnel. The operator should be familiar with the general performance and structure of the machine, and master the prevention, judgment and emergency measures of equipment failure.
2. During the production process, the machine should be suspended when leaving the machine, so that the person leaves the machine and stops.
3. Do not put your fingers close to the knife seat and the chuck during the operation of the machine to prevent pinching.
4. When a fault occurs, it should be shut down immediately, the circuit is short-circuited, smoke is generated, and the power supply should be cut off in case of leakage, and the machine can be turned on after the fault is eliminated, and the equipment must not be overloaded with faults.